Mozambique approves enlarged Rovuma LNG plan ahead of year-end FID

Mozambique's Council of Ministers on 17 November approved ExxonMobil's revised development plan for Rovuma LNG. Capacity rises from 15.2 to 18.6 million tonnes a year; Standard Bank puts the cost at about $30bn.

Location: CABO DELGADO

According to the Rio Times, the plan envisages 12 electric-drive modules, each producing 1.55 million tonnes a year. A single combined-cycle power plant will feed them. ExxonMobil says emissions could fall by up to 40%. According to Oilprice, the plan reserves 25% of the gas produced for the domestic market. The National Petroleum Institute calculates that the state could earn about $121bn over a 25-year production life. ExxonMobil cites state revenue above $140bn for phase 1; that company figure has not been independently verified.

The binding constraints are security and capital. The insurgency in Cabo Delgado halted two onshore projects for years; ExxonMobil lifted force majeure in November 2025. A final investment decision is targeted for end-2026 and has not yet been taken. Sources differ on the start date: the company's project page says 2030, while Bloomberg gives the early 2030s. In October ExxonMobil agreed an asset swap with Eni that raises its stake to 50%. The neighbouring TotalEnergies-led project, a $20bn scheme of 13.1 million tonnes a year, restarted work in 2026.

Talay assessment

Bottom line

The approval clears a regulatory hurdle but brings supply no closer. The first of the 18.6 million tonnes a year could arrive around 2030; it does nothing for today's LNG squeeze. The real thresholds are the year-end investment decision and security in Cabo Delgado. The most likely path is that the decision is taken and a new LNG source outside the Atlantic basin comes online in the early 2030s.

Likely effects

  • Global LNG supplyPositive6 months+

    Rovuma and the neighbouring project together could add 31.7 million tonnes a year, but the effect falls after 2030.

  • Mozambique's public financesPositive6 months+

    Estimates of state revenue range from $121bn to $140bn; both depend on production actually starting.

  • European and Asian buyersPositive6 months+

    A new LNG source that does not depend on the Strait of Hormuz gives buyers more options in negotiating extended-tenor contracts.

Possibilities, ranked

  1. 1
    FID arrives at year-end60%

    ExxonMobil announces the final investment decision at the end of 2026 and the main construction contracts are signed.

    Watch: An ExxonMobil FID announcement by the end of December

  2. 2
    Decision slips into next year30%

    Financing or contract timetables push the decision back by a few months.

    Watch: No offtake agreements or loan package announced

  3. 3
    Security halts work again10%

    New attacks in Cabo Delgado force field work to be suspended.

    Watch: Reports of insurgent attacks around Afungi

Probabilities are calibrated judgement based on the sources, not measurement, and are revised as new information arrives. Not investment advice.

Market reaction

Indicators affected

  • Rovuma LNG capacity▲ 18.6 Mt/yr
  • Estimated cost▲ ≈$30bn

Sources

  1. Oilprice.com — Mozambique Approves Exxon's Redesigned $30 Billion Rovuma LNG Plan
  2. Rio Times — ExxonMobil Gets Mozambique Plan Approval