MediumVI Energy Politics & Supply Security23 November 2026, Monday
Pakistan's only coal conveyor breaks down, cutting unloading to a tenth
The sole coal conveyor at Pakistan International Bulk Terminal in Port Qasim has been out of action since 18 November. Daily unloading has fallen from 30,000 tonnes to 3,000 tonnes.
According to a Dawn report on 23 November, the conveyor was damaged on 18 November while the Pegasus 8 was being discharged. PIBT blamed the failure on the unusually dusty Tanzanian coal and sharp pieces of iron in the cargo. Vessels are now being unloaded manually, and daily capacity has dropped from 30,000 tonnes to 3,000. PIBT said repairs could take 8–10 days.
State-owned Jamshoro Power Company (JPC) has put a figure on the damage. Demurrage on the next 5 vessels could reach 2–3 million dollars, or 556–834 million rupees. With coal stocks running low, JPC expects to forgo roughly 2.2 billion rupees a month in capacity payments. PIBT rejected force majeure claims from generators, JPC among them, arguing that unloading continues, albeit slowly.
The bottleneck is structural. The terminal operates with a single jetty, a single berth and a single conveyor. A second conveyor, proposed in 2021, would have lifted annual capacity from 12 million to 17 million tonnes, but it was never built. The outage is hitting public and private power plants as well as the cement and textile industries. One shipping company has said it will claim compensation for waiting time.
Talay assessment
Bottom line
Pakistan's imported coal flows hang on a single conveyor, and it has been idle since 18 November. If repairs finish within 8–10 days, losses will be confined to demurrage. If they drag on, power-plant stocks will run down and electricity supply will tighten ahead of winter demand. The most likely path is capacity returning in early December, with the cost dispute heading to arbitration.
Likely effects
- Power generationNegativeWeeks
Plants with dwindling coal stocks will curtail output; JPC expects to lose 2.2 billion rupees a month in capacity payments.
- Industrial inputsNegativeWeeks
Cement and textile producers may postpone production schedules as coal deliveries slip.
- Port investmentPositive6 months+
The second conveyor project, pending since 2021, returns to the agenda; it could lift capacity from 12 to 17 million tonnes.
Possibilities, ranked
- 1Repairs finish on schedule55%
The conveyor restarts at the end of November, the queue clears in the first week of December and the demurrage dispute rumbles on.
Watch: PIBT announcing that the conveyor is back in service
- 2Prolonged outage30%
Repairs slip into mid-December, power plants curtail output and load-shedding increases.
Watch: The number of coal carriers waiting at anchor off Port Qasim
- 3Alternative terminal steps in15%
The government diverts coal to other ports and flows partly recover.
Watch: A rerouting decision by the Ministry of Maritime Affairs
Probabilities are calibrated judgement based on the sources, not measurement, and are revised as new information arrives. Not investment advice.
Market reaction
Indicators affected
- Daily unloading▼ 30,000→3,000 t
- Demurrage▲ 2–3 million dollars
- Lost capacity payments▲ 2.2bn rupees/month