Akkuyu's first reactor set for physical start-up within weeks
Energy Minister Bayraktar said on 13 November that physical start-up of Akkuyu's first reactor is expected within a few weeks. The four-reactor plant has a combined capacity of 4.8 GW.
According to Türkiye Today on 13 November, Bayraktar said physical start-up of Unit 1 at the Mersin plant would take place within a few weeks. An official at the Nuclear Regulatory Authority told the Russian state agency TASS that pre-operational testing is still under way and, with intensive work, could be finished by the end of the year. That statement comes from state media. Türkiye is targeting 10 GW of nuclear capacity by 2040 and at least 20 GW by 2050.
The schedule has slipped repeatedly. Sol Haber reported on 6 September 2026 that the first unit was originally due online in 2023; in September Bayraktar set the goal as electricity generation by the end of 2026. The same report says Türkiye has committed to buy 70% of the power from the first two reactors for 15 years at 12.35 cents per kilowatt-hour. The plant is 100% Russian-owned and, once complete, will cover roughly 10% of annual demand.
Our reading: Unit 1 alone will meet only about 2–2.5% of demand, so it will not change the winter gas bill straight away. The real effect shows once all four units are running. Ankara is moving roughly 10% of annual electricity demand off gas and tying it to Russian nuclear fuel and a 15-year, hard-currency offtake guarantee.
Talay assessment
Bottom line
Physical start-up is a tangible milestone for a project running three years late, but commercial output and full power to the grid depend on testing finishing by year-end. Unit 1 will cover only about 2–2.5% of demand, so its effect on this winter's gas bill is limited. The most likely path is first power slipping into the first quarter of 2027.
Likely effects
- Gas importsPositive6 months+
Once all four units are complete, roughly 10% of annual demand will be generated without gas; the need for imported gas in power generation falls over the years.
- Dependence on RussiaNegative6 months+
A 100% Russian-owned plant opens a second energy line tying Ankara to Moscow, on top of the gas contract.
- Electricity costsNegative1–6 months
The offtake guarantee at 12.35 ¢/kWh creates a fixed hard-currency obligation for 15 years.
Possibilities, ranked
- 1First power slips to early 202755%
Physical start-up happens in December, testing overruns and first power reaches the grid in the first quarter of 2027.
Watch: Akkuyu Nükleer announcement of minimum controllable power
- 2Year-end target holds30%
Intensive work finishes testing in December and Unit 1 is connected to the grid before 2026 is out.
Watch: NDK operating licence and a late-December grid connection announcement
- 3Fresh delay15%
A testing or supply problem pushes start-up to mid-2027.
Watch: A revised schedule from the energy ministry
Probabilities are calibrated judgement based on the sources, not measurement, and are revised as new information arrives. Not investment advice.