V Technology Geopolitics & AIMiddle East and North Africa
From the UAE, clean energy pledges do not make Gulf AI data centres clean
- Institution
- Al Habtoor Research Centre
- Author
- Habiba Diaaeldin
- Country · language
- UAE · English
- Affiliation
- Private think tank
Summary
An analysis dated 5 October 2026 by Habiba Diaaeldin of the UAE-based Al Habtoor Research Centre argues that the AI data centre boom and the green transition are not naturally aligned. The core argument is one of timing. A data centre goes up in 1–2 years, while transmission lines and clean generation take far longer, so unmet demand is filled by gas. Citing IEA data, the author notes that data centres consumed 415 TWh in 2024, about 1.5% of global demand. In the base case that rises to 945 TWh by 2030. To 2035, renewables add 450 TWh while gas grows by 175 TWh.
The Gulf section of the analysis separates 3 countries. The UAE has the strongest starting point, with a mix of nuclear, solar and gas. It plans 21.7 GW of new capacity by 2030, of which 12 GW is solar. In the author's view, the Barakah nuclear plant already serves existing users as of 2026, so linking it to a new campus does not automatically count as new clean supply. Citing Wood Mackenzie, she notes that as of 2026 UAE rules bar data centres from signing corporate power purchase agreements. As a result, the large cloud companies cannot use their demand to finance new clean capacity.
In Saudi Arabia, renewable capacity doubled to about 12.3 GW in 2025, yet it met less than 1% of generation in 2024. At the start of 2025, roughly two-thirds of the capacity under construction was gas-fired. In Qatar, data centres alone could draw 1.5–2 GW. Facilities in the Middle East have an average power usage effectiveness of 1.79, behind the global figure of 1.56. The author makes 3 recommendations. Grid connection permits should be tied to additional clean supply. Electricity, water and carbon intensity should be disclosed. Capacity should be phased according to clean generation delivered, not announcement dates.
Blind spot
The analysis reads data centres through the lens of climate accounting. It does not discuss what may be the real constraint on Gulf AI campuses: physical security, exposed by the 2026 war, and US chip export licences. Nor does it quantify how far the LNG and gas price shock from the Strait of Hormuz has eroded the cost advantage of gas-fed data centres.
Talay assessment
Bottom line
The Gulf markets its AI capacity on cheap energy, but on this reading the new load will be met by gas in the near term. Set against global demand growth to 945 TWh, the UAE's 21.7 GW plan and Saudi Arabia's renewable share of under 1% make it hard to tie the clean data centre claim to measurable targets. The most likely path is gas-heavy growth in Gulf campuses, with pressure for transparency coming from European buyers.
Likely effects
- Gas demandNegative6 months+
Meeting data centre load with gas could raise domestic gas consumption in the Gulf and limit the volumes left for export.
- AI investmentNegative1–6 months
Until the ban on corporate power purchase agreements is lifted, cloud companies cannot directly finance new clean capacity in the UAE.
- Efficiency racePositive1–6 months
If new UAE facilities bring power usage effectiveness below 1.5, from a regional average of 1.79, the Gulf keeps its energy cost advantage.
Possibilities, ranked
- 1Gas-heavy growth60%
Campuses go up quickly, the load is met by gas, and the clean energy claim rests on certificate accounting.
Watch: New gas plant tenders and data centre grid connection permits in the UAE and Saudi Arabia
- 2Regulatory reform25%
The UAE allows corporate power purchase agreements, and cloud companies directly finance solar capacity.
Watch: A change to the PPA rule by the UAE energy regulator
- 3Capacity slows15%
Security and cost risks delay announced projects.
Watch: A major Gulf AI campus pushing back its timetable
Probabilities are calibrated judgement based on the sources, not measurement, and are revised as new information arrives. Not investment advice.
Original publication: habtoorresearch.com · 5 October 2026
This page summarises the institution's view and does not reflect the view of Talay Insight. No direct quotation is used.