ISEAS sees Malaysia's renewables boom tied to data centre debt

Singapore Strait and Pasir Panjang Port Terminal (2016)Photo: Bob Tan / Wikimedia Commons · CC BY-SA 4.0 · resized · Source
Institution
ISEAS – Yusof Ishak Institute (Fulcrum)
Author
James Chai
Country · language
Singapore · English
Affiliation
Government-linked research institute

Summary

Writing in Fulcrum on 18 November, former ISEAS visiting fellow James Chai examined Malaysia's renewable energy boom. In his view the sector depends more on policy than on demand. In 2019 the grid's reserve margin exceeded 30%, which is why solar quotas were kept low. The 2023 National Energy Transition Roadmap raised the renewables target to 70% of the power mix. In 2025 the share was 32%.

Data centres are carrying demand. By June 2026 data centres had reserved 8.35 GW of capacity from the national utility TNB. That is more than a third of peninsular Malaysia's record peak demand and close to Singapore's August 2026 peak of 8.6 GW. The government requires data centres to source at least 30% of their power from renewables. Analysts estimate this could open a 36 billion ringgit opportunity. TNB plans 43 billion ringgit of grid investment. Google wants to buy 1 GW of renewables through the CRESS programme.

Chai sees the risk in debt. Global data centre spending is largely debt-financed. A Gartner estimate cited in the piece says $3.5 trillion of AI infrastructure faces impairment risk by 2030. If AI investment stalls, solar and grid assets could be stranded. If demand climbs too high, coal plants slated for retirement could come back. In Johor about a third of data centre applications were rejected in 2024, and 24 applications await water and power reviews.

Blind spot

The piece notes that most solar equipment comes from China but does not discuss how US export controls on chips and data centres could cut Malaysian demand. Nor does it say how much of the 8.35 GW reserved will actually be built; the gap between reserved capacity and power actually drawn remains unclear.

Talay assessment

Bottom line

Chai's reading shows Malaysia's energy transition locked into the AI investment cycle. The 8.35 GW of reservations changes the scale of the grid, but the contracts rest on debt-financed demand. The most likely path is that the government slows growth with tighter approvals and the coal exit timetable stays under pressure.

Likely effects

  • Power supplyNegative1–6 months

    If data centre demand outruns grid capacity, coal plants due for retirement stay online and the 70% renewables target slips.

  • Renewables investmentPositiveWeeks

    The 30% renewables requirement and the CRESS programme create 36 billion ringgit of business and a flow of orders for local solar firms.

  • Stranded asset riskNegative6 months+

    If AI spending slows, TNB's 43 billion ringgit grid investment and solar farms are left with low utilisation.

Possibilities, ranked

  1. 1
    Selective growth55%

    The government ties approvals to water and power reviews, some reservations turn into construction and the renewables share rises slowly.

    Watch: Decisions on the 24 pending data centre applications in Johor

  2. 2
    Demand surge brings coal back25%

    Peak demand grows faster than renewable additions and the lives of coal plants due to close are extended.

    Watch: An announcement delaying the coal plant retirement schedule

  3. 3
    AI investment stalls20%

    Data centre projects are cancelled or postponed, leaving solar and grid investments with idle capacity.

    Watch: Cancellations of data centre reservations or TNB revising the 8.35 GW figure down

Probabilities are calibrated judgement based on the sources, not measurement, and are revised as new information arrives. Not investment advice.

Original publication: fulcrum.sg · 18 November 2026

This page summarises the institution's view and does not reflect the view of Talay Insight. No direct quotation is used.